By Lava Smirnova

Unit 1 of Bangladesh’s first nuclear power plant has been connected to the grid, while Turkey’s Akkuyu NPP has started the penultimate stage of tests before start-up operations.

Unit 1 of Rooppur Nuclear Power Plant (NPP) (the Rosatom project) has been successfully synchronised with the national grid of Bangladesh. The first megawatts generated at the plant reached the country’s power system. The reactor reached 40% of its rated power – this is the point at which the generator can be connected to the grid for the first time. The generator output stood at 370 MW.

“The power start-up of Unit 1 of Rooppur NPP is a landmark event for our two countries. Bangladesh is gaining a reliable, stable and environmentally friendly source of energy that will significantly reduce the country’s dependence on imported hydrocarbons. Nuclear power also provides Bangladesh with access to advanced technologies and contributes to the development of engineering expertise and scientific research. For Russia and Rosatom, the power start-up of Unit 1 of Rooppur NPP marks another successfully implemented project, demonstrating our country’s undisputed leadership in the global nuclear technology market,” highlighted Rosatom Director General Alexey Likhachev.

Africa’s first plant with the same technology is under construction in Egypt. El-Dabaa NPP is the continent’s first Generation III+ nuclear power plant. All four of its units are being built at the same time, and around 26,000 people work at the site, most of them Egyptian nationals. Reactor pressure vessels are already in place at Units 1 and 2. Delivery of the first batch of fuel for Unit 1 is planned for 2027.

Turkey, another country building its first nuclear power plant with Rosatom, is also approaching start-up. Unit 1 of Akkuyu NPP has started hot functional testing, the penultimate stage of tests before start-up operations. All equipment of the reactor plant is being tested in operating modes before nuclear fuel is loaded for the first time.

As of June 2026, Rosatom is building 28 of the 32 power units under construction by nuclear vendors outside their home markets. In October, Alexey Likhachev confirmed that Rosatom is ready to supply African countries with nuclear power plants of various sizes and configurations. “Our partnership is based on the principle that Africa is diverse, and we have a tailored approach for each country that goes beyond a single project,” he noted.

 Rooppur NPP, comprising two power units with VVER-1200 reactors and a total installed capacity of 2,400 MW, is being built to a Russian design about 160 km from Dhaka, the capital of Bangladesh. The general contract was signed on 25 December 2015. The VVER-1200 reactor is Rosatom’s flagship technology. It has demonstrated its efficiency and reliability through the operation of reference units, belongs to Generation III+ and fully complies with modern international safety requirements.

Six power units with VVER-1200 reactors are in operation: four in Russia and two in the Republic of Belarus. Abroad, Rosatom is building 26 power units with VVER reactors: four each in China, India, Turkey and Egypt, and two each in Bangladesh, Iran, Hungary, Uzbekistan and Kazakhstan.

Akkuyu NPP is the first nuclear power plant under construction in the Republic of Turkey. It will comprise four power units with Russian-designed Generation III+ VVER reactors, each with a capacity of 1,200 MW. It is the first project in the global nuclear industry implemented under the Build-Own-Operate model.

Rosatom’s Engineering Division brings together leading companies of the nuclear industry, including the management company Atomstroyexport JSC, the integrated design institute Atomenergoproekt JSC and subsidiary construction organisations. The Division ranks first in the world by order portfolio and by the number of nuclear power plants under simultaneous construction in different countries. International projects account for about 80% of its revenue.